AGENDA RECOMMENDATION |
Consent Calendar 5.G.
City Council Regular Meeting
- Meeting Date:
- 08/25/2025
Agenda Item:
Motion approving change orders for All Seasons Arena.
Recommendation/Action(s):
Motion approving change orders.
Summary:
Staff is recommending approval of the following change orders. The All Seasons Arena Board approved these at their August 8th meeting.
Met-Con, Trade Package 1A
Change Order #16, $316.83
CO #16 includes the following:
Malterer Mechanical, Trade Package 23B
Change Order #10, $500.00
CO #10 includes the following:
Laketown Electric, Trade Package 26A
Change Order #10, $11,020.00
CO #10 includes the following:
The above change orders will increase the overall project cost by $11,836.83. If approved, the contingency will be decreased to $104,464.85.
Staff recommends a motion approving the change orders.
Met-Con, Trade Package 1A
Change Order #16, $316.83
CO #16 includes the following:
- Installation of owner supplied flooring to replace degraded flooring near the north rink Zamboni entrance
- Painting changes for ease of maintenance – removal of stripes in lobby and north rink mezzanine
- Omit wall guard in lobby for consistent wall finish
- Removal of a floor drain in new office location – concrete removal and repair
Malterer Mechanical, Trade Package 23B
Change Order #10, $500.00
CO #10 includes the following:
- Removal of a floor drain in new office location – cap drain below floor
Laketown Electric, Trade Package 26A
Change Order #10, $11,020.00
CO #10 includes the following:
- Code required lighting changes to the main building signage
- Additional exit/emergency lights required by code in the lobby
- 2 emergency lights on the north side of the north rink that are inoperable and need replacement.
The above change orders will increase the overall project cost by $11,836.83. If approved, the contingency will be decreased to $104,464.85.
Staff recommends a motion approving the change orders.