5.13.
CC Regular Session
Meeting Date:
09/22/2020
Submitted For:
Bruce Westby
By:
Marsha Weidner, Engineering/Public Works

Information

Title

Adopt Resolution #20-200 Authorizing Final Payment to Allied Blacktop Company for Improvement Project #20-00, 2020 Crack Sealing Improvements.

Purpose/Background:

Resolution and Pay Request Attached.

Observations/Alternatives:

Issuing final payment will be contingent on receipt of the following items from Allied Blacktop Company.
  1. IC 134 (Contractor’s Withholding Affidavit showing compliance with the provisions of Minnesota Statute 290.92 requiring withholding state income tax).
  2. Waiver of Mechanic’s Lien Rights (Affidavits that all claims against Allied Blacktop Company by reasons of the contract have been fully paid or satisfactorily secured).
  3. Consent of Surety to Final Payment (Certification from the contractor’s surety).
Following receipt of these items, final payment will be issued.
 

Recommendation:

The Engineering Technician IV has inspected the completed work and recommends final payment to Allied Blacktop Company  for Improvement Project #20-00, 2020 Crack Sealing Improvement in the amount of $96,554.00.

Action:

Motion to adopt Resolution #20-200 Authorizing Final Payment to Allied Blacktop Company for Improvement Project #20-00, 2020 Crack Sealing Improvements in the amount of $96,554.00.

Attachments

Form Review

Inbox Reviewed By Date
Bruce Westby Bruce Westby 09/16/2020 01:57 PM
Bruce Westby Bruce Westby 09/16/2020 02:10 PM
Bruce Westby Bruce Westby 09/16/2020 02:10 PM
Kurt Ulrich Kurt Ulrich 09/17/2020 03:39 PM
Form Started By:
Marsha Weidner
Started On:
09/14/2020 08:36 AM
Final Approval Date:
09/17/2020