29.
Commissioners Court Meeting
- Meeting Date:
- 10/28/2024
- Title:
- Award CSP 2024-008 ARPA Waterline Projects 4,5,9,10,12, & 13 Rio Bravo WTP to La Presa
- Submitted for:
- Joe Lopez
- Submitted By:
- Joe Lopez
- Department:
- Purchasing
Subject:
Discussion and possible action to accept the rankings and award Competitive Sealed Proposal (CSP) 2024-008 “ARPA Waterline Projects 4, 5, 9, 10, 12, & 13 Rio Bravo Water Treatment Plant to La Presa" to the highest ranking respondent. The scope of work consist of providing water supply from Rio Bravo Water Treatment Plant (RBWTP) located at 512 Martha Street to Colonia La Presa located approximately five (5) miles north of the RBWTP, about two (2) miles east from US Hwy. 83 and Mangana Hein Road intersection pursuant to the Texas Government Code; §2269.151 Contracts for Facilities: Competitive Sealed Proposals and with the Code of Federal Regulations §200.318 - §200.327 (General Procurement Standards) and to further authorize the Webb County Judge to execute a contract between Webb County and selected respondent for the awarded sum and any other matters incident thereto. [Account #2703-5205-001-474501- (American Rescue Plan Act of 2021-American Rescue Plan-Administration-Construction In Progress-Rio Bravo to La Presa Waterline Ext. Project]
Issue: This public works project was authorized by Webb County Commissioners Court to be funded as part of its allocation of American Rescue Plan Act Funds awarded to Webb County.
Solution: Consideration to accept the rankings and award to the highest ranking respondent based on the base bid and alternate options recommended by the Project Engineer. Eight (8) formal proposals were officially received by solicitation deadline.
Result: If approved, a construction contract will be prepared by General Counsel to include any required federal contract provisions for final approval by Webb County Commissioners Court.
Issue: This public works project was authorized by Webb County Commissioners Court to be funded as part of its allocation of American Rescue Plan Act Funds awarded to Webb County.
Solution: Consideration to accept the rankings and award to the highest ranking respondent based on the base bid and alternate options recommended by the Project Engineer. Eight (8) formal proposals were officially received by solicitation deadline.
Result: If approved, a construction contract will be prepared by General Counsel to include any required federal contract provisions for final approval by Webb County Commissioners Court.
Background:
N/A
Previous Court Action:
Fiscal Impact
- Budget Account Number:
- 2703-5202-001-01
- Funding Source:
- Construction in Prog
- Balance:
- TBD
Financial Impact:
2703-5205-001-474501- (American Rescue Plan Act of 2021-American Rescue Plan-Administration-Construction In Progress-Rio Bravo to La Presa Waterline Ext. Project
***ARPA sub - account needs to be created by County Auditors***
***ARPA sub - account needs to be created by County Auditors***