23.
Commissioners Court Meeting
- Meeting Date:
- 10/28/2024
- Title:
- Highway 359 Mailbox Relocation Project
- Submitted for:
- Fortunato Paredes
- Submitted By:
- Fortunato Paredes
- Department:
- Civil Legal Division
Subject:
Discussion and possible Action to enter into a contractual agreement with SIMA Contractors, LLC for a Mailbox Relocation project along State Highway 359 for an amount not to exceed ONE HUNDRED FIFTY-FIVE THOUSAND FIVE HUNDRED FIFTY DOLLARS ($155,550.00) and any other matters incident thereto, and authorizing the County Judge to sign all relevant documents and any other matters incident thereto. [Account #2007-7150-001-470000 (Capital Outlay)]
Issue: Existing individual mailboxes along the shoulder/roadside on South Highway 359 serving residents living off Wawi Tijerina Parkway, Emiliano Road, and Welsch Road are in need of replacement.
Solution: At the Commissioners Court meeting of October 4, 2024, the court awarded ITB 2024-009 “Webb County HWY 359 Mailbox Relocation Project to SIMA Contractors, LLC to do the Mailbox (Cluster Mailboxes) relocation work.
Result: The Contractor will substantially complete the project within ninety (90) calendar days from the issuance of the “Notice to Proceed” by the Engineering Department.
Issue: Existing individual mailboxes along the shoulder/roadside on South Highway 359 serving residents living off Wawi Tijerina Parkway, Emiliano Road, and Welsch Road are in need of replacement.
Solution: At the Commissioners Court meeting of October 4, 2024, the court awarded ITB 2024-009 “Webb County HWY 359 Mailbox Relocation Project to SIMA Contractors, LLC to do the Mailbox (Cluster Mailboxes) relocation work.
Result: The Contractor will substantially complete the project within ninety (90) calendar days from the issuance of the “Notice to Proceed” by the Engineering Department.
Background:
Existing mailboxes along the shoulder/roadside on South Highway 359 are in need of being replaced.
Previous Court Action:
None
Fiscal Impact
- Budget Account Number:
- 2007-7150-001-470000
- Funding Source:
- Capital Outlay
- Balance:
- N/A
Financial Impact:
$155,550.00