Commissioners Court Meeting
- Meeting Date:
- 02/10/2025
- Title:
- APPROVAL OF CHANGE ORDER FOR ARPA PROJECT NO. 0025-EL PICO ROAD WIDENING AND PAVING PROJECT
- Submitted for:
- Martha Palacios
- Submitted By:
- Martha Palacios
- Department:
- Engineering
Subject:
Discussion and possible action to approve an additive Change Order (No. 1) to Anderson Columbia Co., Inc., for Material Testing, in the total amount of $42,692.00 for ARPA Project No. 0025-Webb County CSP 2025-01 El Pico Road Widening and Paving Improvement Project; and have the County Judge sign any relevant documents; and any other matters incident thereto. [Account #2703-5205-006-474501-104 (Construction in Progress - $5,876,920.00 El Pico Road Project)]
Issue: Material Testing is needed for quality control based on Project Engineer's preliminary plans.
Solution: The intent is to use part of the project's contingency allowance to fund the material testing.
Result: Quality control will be done on materials provided by the contractor.
Issue: Material Testing is needed for quality control based on Project Engineer's preliminary plans.
Solution: The intent is to use part of the project's contingency allowance to fund the material testing.
Result: Quality control will be done on materials provided by the contractor.
Background:
N/A
Previous Court Action:
N/A
Fiscal Impact
- Budget Account Number:
- 0
- Funding Source:
- 0
- Balance:
- 0
Financial Impact:
2703-5205-006-474501-104 Construction In Progress-$5,876,920.00 El Pico Road Project