Subject:
Discussion and possible action to approve Change Order No. 1 (Rain Days) for Quantcorp Construction LLC., for ARPA Project No. 002-Southern Fire Station. The contract sum will not be increased by this Change Order; and authorize the Webb County Judge to sign any relevant documents; and any other matters incident thereto. [No Impact to the Account]
Issue: Due to several weather-related delays in the months of June, July, September, December 2024 and January 2025, the current substantial completion date will be extended.
Solution: Approval of Change Order. The new contract time will be increased by twenty-nine (29) days.
Result: Substantial completion date will be from April 6, 2025 to May 5, 2025.
Issue: Due to several weather-related delays in the months of June, July, September, December 2024 and January 2025, the current substantial completion date will be extended.
Solution: Approval of Change Order. The new contract time will be increased by twenty-nine (29) days.
Result: Substantial completion date will be from April 6, 2025 to May 5, 2025.
Background:
N/A
Previous Court Action:
N/A
Fiscal Impact
- Budget Account Number:
- 0
- Funding Source:
- 0
- Balance:
- 0
Financial Impact:
No Impact