CHANGE ORDER FOR ADDITIONAL DAYS
Submitted for:
Martha Palacios
Submitted By:
Martha Palacios
Department:
Engineering

Subject:

Discussion and possible action to approve Change Order No. 1 Additional Days for Midas Contractors, LLC., for ARPA Project No. 0008-Webb County Community Action Agency Administration, Social Services & Meals on Wheels Project. The Contract Sum will not be increased by this Change Order; and authorize the Webb County Judge to sign any relevant documents; and any other matters incident thereto. [No impact to the account]
 
Issue: The following items have impacted the progress of the project:
  • Install furr wall to cover rough finish due to demolition of tile.
  • Cut and cap a 6” water line that was found (not in plans) during the excavation of a storm drain line.
  • Installation of carpet as requested by CAA in the Manager’s office.
  • Ice maker relocation requested by CAA.

Some of the listed items and other items are due to relocation and/or demolition due to remodeling. These and other items may be found on the attached documents. The completion date will be extended thirty (30) calendar days.
 
Solution: Approval of Change Order which will increase the contract time by thirty (30) days.

Result: Substantial completion date will be from September 21, 2025 to October 21, 2025.

Background:

N/A

Previous Court Action:

N/A

Fiscal Impact

Budget Account Number:
0
Funding Source:
0
Balance:
0

Financial Impact:

No Fiscal Impact