45.
Commissioners Court Meeting
- Meeting Date:
- 07/14/2025
- Title:
- Construction Manager at Risk (Leyendecker Construction of Texas, Inc.) Guaranteed Maximum Price for Package 1, Phase 2
- Submitted for:
- Nathan Bratton
- Submitted By:
- Nathan Bratton
- Department:
- Commissioners Court
Subject:
Discussion and possible action to consider Construction Manager at Risk (Leyendecker Construction of Texas, Inc.) Guaranteed Maximum Price for Package 1, Phase 2 (includes but is not limited to Site work, Utilities and Drainage) for the Webb County Fairgrounds Project at a cost of Twenty Million Nine Hundred Seventy Thousand Eleven Dollars and Thirty-five cents ($20,970,011.35) and any matters incident thereto; authorizing the County Judge to sign all relevant documents. [Funding Source: Account #3901-7230-001-474501 (Construction in Progress)]
Issue: Commissioners Court approved a Contract with Leyendecker Construction of Texas, Inc. (“CMAR”) to undertake the construction of a rodeo arena and multi-purposae exhibition hall with parking (“Project”) contingent on approval of a Guaranteed Maximum Price (“GMP”) for the project.
Solution: If the Court accepts the Guaranteed Maximum Price, Leyendecker Construction of Texas, Inc.will be contractually bound to undertake the Project and substantially complete the Project.
Result: Acceptance of the GMP will allow for the CMAR to do the work.
Issue: Commissioners Court approved a Contract with Leyendecker Construction of Texas, Inc. (“CMAR”) to undertake the construction of a rodeo arena and multi-purposae exhibition hall with parking (“Project”) contingent on approval of a Guaranteed Maximum Price (“GMP”) for the project.
Solution: If the Court accepts the Guaranteed Maximum Price, Leyendecker Construction of Texas, Inc.will be contractually bound to undertake the Project and substantially complete the Project.
Result: Acceptance of the GMP will allow for the CMAR to do the work.
Background:
Issue: Commissioners Court approved a Contract with Leyendecker Construction of Texas, Inc. (“CMAR”) to undertake the construction of a rodeo arena and multi-purposae exhibition hall with parking (“Project”) contingent on approval of a Guaranteed Maximum Price (“GMP”) for the project.
Solution: If the Court accepts the Guaranteed Maximum Price, Leyendecker Construction of Texas, Inc.will be contractually bound to undertake the Project and substantially complete the Project .
Result: Acceptance of the GMP will allow for the CMAR to do the work.
Solution: If the Court accepts the Guaranteed Maximum Price, Leyendecker Construction of Texas, Inc.will be contractually bound to undertake the Project and substantially complete the Project .
Result: Acceptance of the GMP will allow for the CMAR to do the work.
Previous Court Action:
Fiscal Impact
- Budget Account Number:
- 3901-7230-001-474501
- Funding Source:
- Construction in Prog
- Balance:
- unknown
Financial Impact:
Package 1, Phase 2 (includes but is not limited to Site work, Utilities and Drainage) for the Webb County Fairgrounds Project at a cost of Twenty Million Nine Hundred Seventy Thousand Eleven Dollars and Thirty-five cents ($20,970,011.35)