12.a.
Commissioners Court Meeting
Meeting Date:
08/12/2024
Title:
APPROVAL OF CHANGE ORDER NO. 1 FOR ARPA PROJECT NO. 1 - SOUTHERN FIRE STATION-RAIN DAYS
Submitted for:
Martha Palacios
Submitted By:
Martha Palacios
Department:
Engineering

Subject:

Discussion and possible action to approve Change Order No. 1 (Rain Days) for Quantcorp Construction LLC., for ARPA Project No. 2-Southern Fire Station. The Contract Sum will not be increased by this Change Order; and authorize the Webb County Judge sign any relevant documents; and any other matters incident thereto. [No impact to the account]

Issue: Rain days on the month of June 2024, June 12, 13, and 14 (3 days). Dry off days, June 15, 16, and 17 (3 days). Total weather delayed days for June 2024; 6 days.

Solution: Approval of Change Order. The new contract time will be increased by six (6) days.

Result: The new date of Substantial Completion will be April 12, 2025.

Background:

N/A

Previous Court Action:

N/A

Fiscal Impact

Budget Account Number:
0
Funding Source:
0
Balance:
0

Financial Impact:

No Impact