13.a.
Commissioners Court Meeting
Meeting Date:
02/24/2025
Title:
CHANGE ORDER FOR ARPA PROJECT NO. 0002-SOUTHERN FIRE STATION
Submitted for:
Martha Palacios
Submitted By:
Martha Palacios
Department:
Engineering

Subject:

Discussion and possible action to approve Change Order No. 1 (Rain Days) for Quantcorp Construction LLC., for ARPA Project No. 002-Southern Fire Station. The contract sum will not be increased by this Change Order; and authorize the Webb County Judge to sign any relevant documents; and any other matters incident thereto. [No Impact to the Account]

Issue: Due to several weather-related delays in the months of June, July, September, December 2024 and January 2025, the current substantial completion date will be extended.

Solution: Approval of Change Order. The new contract time will be increased by twenty-nine (29) days.

Result: Substantial completion date will be from April 6, 2025 to May 5, 2025.

Background:

N/A

Previous Court Action:

N/A

Fiscal Impact

Budget Account Number:
0
Funding Source:
0
Balance:
0

Financial Impact:

No Impact