Subject:
Discussion and possible action to enter into Amendment #4 with Garver’s Construction Administration Services shall be extended to align with the full 810 calendar day construction duration of the awarded construction contract. This amendment adds 445 additional calendar days of Construction Administration Services beyond the original 365-day scope outlined in Task 5 of the original Agreement's Scope of Services in a lump sum amount of One Hundred Thirty-Nine Thousand Nine Hundred Sixteen Dollars ($139,916.00). [Account #1001-1130-001-431007-010 (Operational Reserve)]