27.
Commissioners Court Meeting
- Meeting Date:
- 01/26/2026
- Title:
- CLOSEOUT AND RELEASE OF RETAINAGE FOR THE FESCO BUILDING FLOOR PROJECT
- Submitted for:
- Martha Palacios
- Submitted By:
- Martha Palacios
- Department:
- Engineering
Subject:
Discussion and Possible Action to approve the Closeout and Release of Retainage in the amount of $5,190.00 to Quantcorp Construction, LLC., for the completion of the FESCO Building Floor Project; and have the County Judge sign any relevant documents and any other matters incident thereto. [Account #2007-206000 (Retainage Payable)]
Issue: Due to wear and tear of rugs from previous owners at the FESCO Building, floors had to be replaced.
Solution: Epoxy flooring was installed. Approve and release retainage amount and close out project.
Result: Completion of project.
Issue: Due to wear and tear of rugs from previous owners at the FESCO Building, floors had to be replaced.
Solution: Epoxy flooring was installed. Approve and release retainage amount and close out project.
Result: Completion of project.
Background:
N/A
Previous Court Action:
N/A
Fiscal Impact
- Budget Account Number:
- 0
- Funding Source:
- 0
- Balance:
- 0
Financial Impact:
Account #2007-206000 (Retainage Payable)