Subject:
Discussion and possible action to approve Change Order #7 with AOC Calton, Ltd. d/b/a Summit Building & Design for an increase of 40 days for a final date of March 31, 2026, to allow completion of construction on the Webb County Southern Health Facility Project, contingent on approval from state funding agency and authorizing the County Judge to execute all relevant documents and any other matters incident thereto.
Issue: The contract with Summit Building & Design is due to expire on February 19, 2026 and construction is still ongoing.
Solution: Approve Change Order #7 in order to Summit Building & Design to have additional days to complete construction.
Result: Additional days will allow for project completion within an approved contract timeline.
Issue: The contract with Summit Building & Design is due to expire on February 19, 2026 and construction is still ongoing.
Solution: Approve Change Order #7 in order to Summit Building & Design to have additional days to complete construction.
Result: Additional days will allow for project completion within an approved contract timeline.
Background:
n/a
Previous Court Action:
n/a
Fiscal Impact
- Budget Account Number:
- n/a
- Funding Source:
- n/a
- Balance:
- n/a
Financial Impact:
n/a