46.
Commissioners Court - Regular Session
- Meeting Date:
- 03/20/2018
- Title:
- North Campus Facility P324 - Change Order 48
- Submitted By:
- Gina Wrehsnig, Infrastructure
- Department:
- Infrastructure
- Division:
- Building Maintenance
- Agenda Category:
- Regular Agenda Items
Information
Agenda Item
Discuss, consider and take appropriate action on the Williamson County North Campus Project; Change Order #48 from Vaughn Construction in the amount of $35,771.00 to fund concrete work at infill gap along sidewalk and drive that was not included in the original scope of the project. This change order is being funded by the Owners Contingency.
Background
The scope of concrete work for this change order is necessary to prevent water intrusion underneath the asphalt paving of the driveway. This infill was not specified in the original design documents but was clarified in ASI-042.
Fiscal Impact
| From/To | Acct No. | Description | Amount |
|---|
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| County Judge Exec Asst. | Wendy Coco | 03/15/2018 11:21 AM |
- Form Started By:
- Gina Wrehsnig
- Started On:
- 03/15/2018 10:30 AM
- Final Approval Date:
- 03/15/2018