30.
Commissioners Court - Regular Session
- Meeting Date:
- 01/19/2021
- Title:
- Final plat for the Santa Rita Ranch South Section 8B subdivision – Pct 2
- Submitted For:
- Terron Evertson
- Submitted By:
- Adam Boatright, Infrastructure
- Department:
- Infrastructure
- Division:
- Road & Bridge
- Agenda Category:
- Consent
Information
Agenda Item
Discuss, consider and take appropriate action on approval of the final plat for the Santa Rita Ranch South Section 8B subdivision – Precinct 2.
Background
This is the next section of the Santa Rita Ranch South development. It consists of 58 single family lots, 2 landscape lots, 1 park lot and 1,851 linear feet of new public roads. Roadway and drainage construction are not yet complete but a financial security in the amount of $677,467.25 has been posted with the County to cover the cost of the remaining construction.
Timeline
2020-05-29 – initial submittal of the final plat
2020-06-26 – 1st review complete with comments
2020-12-30 – 2nd submittal of final plat
2021-01-11 – 2nd review complete with comments cleared except for completing construction
2021-01-12 – receipt of final plat with all signatures
2021-01-13 – receipt of a financial security in the amount of the remaining construction
2021-01-14 – final plat placed on the January 19, 2021 Commissioners Court agenda for consideration
Timeline
2020-05-29 – initial submittal of the final plat
2020-06-26 – 1st review complete with comments
2020-12-30 – 2nd submittal of final plat
2021-01-11 – 2nd review complete with comments cleared except for completing construction
2021-01-12 – receipt of final plat with all signatures
2021-01-13 – receipt of a financial security in the amount of the remaining construction
2021-01-14 – final plat placed on the January 19, 2021 Commissioners Court agenda for consideration
Fiscal Impact
| From/To | Acct No. | Description | Amount |
|---|
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| County Judge Exec Asst. | Andrea Schiele | 01/14/2021 11:33 AM |
- Form Started By:
- Adam Boatright
- Started On:
- 01/14/2021 11:29 AM
- Final Approval Date:
- 01/14/2021