T5045 - CR 404 Hutto Water Line Realignment Change Order #2 (Jonah Water Line)
Submitted By:
Julissa Vasquez, Road Bond
Department:
Road Bond
Agenda Category:
Regular Agenda Items

Information

Agenda Item

Discuss, consider, and take appropriate action regarding Change Order No. 2 in the amount of $625,239.52 for Project T5045 CR 404 Hutto Water Line Realignment (Austin Underground) P: 390b Funding Source: Road Bond.

Background

This Change Order adds the relocation of the Jonah Water line along CR 401 that is currently in conflict with the CR 401 Reconstruction project.

The following new items will be added by this Change Order.
 
ITEM DESCRIPTION QUANTITY UNIT
J106-01 4" C-900 DR-18 PVC Pipe and Fittings, w/ Tracer Wire; Installed 1,372.00 LF
J106-02 4" C-900 DR-18 PVC Restrained Joint Pipe and Fittings, w/ Tracer Wire; Installed 202.00 LF
J106-03 2" HDPE SDR 9 and Fittings; w/ Tracer Wire; Installed 7.00 LF
J106-04 20" Steel Enc. Pipe, Bored; w/ 4" Restrained Joint C900 DR18 PVC Pipe; Installed 295.00 LF
J106-05 20" Steel Enc. Pipe, Open Cut; w/ 4" Restrained Joint C900 DR18 PVC Pipe; Installed 265.00 LF
J106-06 8" Steel Enc. Pipe, Open Cut; w/ 4" Restrained Joint C900 DR18 PVC Pipe; Installed 208.00 LF
J106-07 Concrete Encased; 8" Steel Enc. Pipe, Open Cut; 4" Restrained Joint C900 DR 18 PVC Pipe; Installed 200.00 LF
J106-08 4" Gate Valve, Box, and Marker; Installed 9.00 EA
J106-09 Air/Vacuum Relief Valve Assembly and Marker; Installed 1.00 EA
J106-10 Blow Off Valve Assembly And Marker; Installed 2.00 EA
J106-11 Connect New 4" to Existing 4"; Installed 2.00 EA
J106-12 Connect New 4" to Existing 2"; Installed 3.00 EA
J106-13 Connect New 2" To Existing 1.5"; Installed 1.00 EA
J106-14 Cap Existing 2" Line; Complete 1.00 EA
J106-15 Trench Safety System Design and Implementation 2,254.00 LF
J106-16 Traffic Control Plan Development And Implementation 1.00 LS
J106-17 SWPPP Design and Implementation 1.00 LS
J106-18 Mobilization (Not to Exceed 10% of Total Project Bid) 1.00 LS

This Change Order results in an increase of $625,239.52 to the Contract amount, for an adjusted Contract total of $3,290,328.25. The original Contract amount was $2,897,639.00. As a result of this and all Change Orders to-date, $392,689.25 has been added to the Contract, resulting in a 13.55% net increase to the overall Contract cost. Due to the current uncertainty in material lead times, time adjustments for this work will be deferred to a later time. Additional time will be determined once materials are on site and will only be granted after the completion of the original scope of work.

Fiscal Impact

Attachments

Form Review

Inbox Reviewed By Date
County Judge Exec Asst. Becky Pruitt 07/07/2022 09:55 AM
Form Started By:
Julissa Romero
Started On:
07/06/2022 10:06 AM
Final Approval Date:
07/07/2022