Discuss, consider and take appropriate action to approve an amendment to the Agreement for Construction Services for the construction of an On-Site Sewage Facility (OSSF) at the Bridge Church, in relation to the Southeast Loop Segment 1 Project. Funding Source: Road Bond P463.
Background
This Amendment No. 1 amends the scope of work to include additional electrical work to connect the OSSF system to the power service. The addition of this work does not change the project duration. The Contract Price is increased by $945.64 for a total Contract Price of $39,795.64.
Fiscal Impact
| From/To | Acct No. | Description | Amount |
|---|
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| County Judge Exec Asst. | Becky Pruitt | 08/18/2022 10:01 AM |
- Form Started By:
- Julissa Romero
- Started On:
- 08/16/2022 10:52 AM
- Final Approval Date:
- 08/18/2022