Commissioners Court - Regular Session
- Meeting Date:
- 09/13/2022
- Title:
- Children’s Advocacy Center Addition (P530) – Vaughn Change Order 2
- Submitted For:
- Dale Butler
- Submitted By:
- Wendy Danzoy, Facilities Management
- Department:
- Facilities Management
- Agenda Category:
- Consent
Information
Agenda Item
Discuss, consider and take appropriate action on Vaughn Construction, Change Order No. 2 for the Children’s Advocacy Center Addition project (P530) for $108,537. No time extension is required. Funding Source is P530.
Background
This change order is to increase contract by $108,537 for changes in observation room and addition of partition. There will be no time added to completion. Department point of contact is Sr. Project Manager, Angel Gomez.
Fiscal Impact
| From/To | Acct No. | Description | Amount |
|---|
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Hal Hawes | Hal Hawes | 08/31/2022 04:31 PM |
| Facilities Management | wendy.danzoy | 09/01/2022 11:26 AM |
| Hal Hawes | Hal Hawes | 09/01/2022 12:54 PM |
| County Judge Exec Asst. | Becky Pruitt | 09/01/2022 02:12 PM |
- Form Started By:
- wendy.danzoy
- Started On:
- 08/31/2022 12:41 PM
- Final Approval Date:
- 09/01/2022