73.
Commissioners Court - Regular Session
- Meeting Date:
- 09/13/2022
- Title:
- T5023 CR 200 Reconstruction Change Order #1 (Various Items)
- Submitted By:
- Julissa Vasquez, Road Bond
- Department:
- Road Bond
- Agenda Category:
- Regular Agenda Items
Information
Agenda Item
Discuss, consider, and take appropriate action regarding Change Order No. 1 in the amount of $26,798.12 for Project T5023 CR 200 Reconstruction (MA Smith Contracting) P: 285 Funding Source: Road Bond.
Background
This Change Order adds items for small signs to the contract that were identified in the plans, but not accounted for in the bid tabs. It also adds items for stripe elimination that were not included in the plans, but necessary for the tie-ins at each end of the project.
This Change Order also adds an item for lowering an existing AT&T communications line that was encountered during the Culvert 1 installation near the west ROW line.
Following is a summary of new items required for this Change Order.
This Change Order results in a net increase of $26,798.12 to the Contract amount, for an adjusted Contract total of $5,002,313.21. The original Contract amount was $4,975,515.09. As a result of this and all Change Orders to-date, $26,798.12 has been added the Contract, resulting in an 0.54% net increase in the Contract cost. No additional days will be added to or deducted from the Contract because of this Change Order.
This Change Order also adds an item for lowering an existing AT&T communications line that was encountered during the Culvert 1 installation near the west ROW line.
Following is a summary of new items required for this Change Order.
| ITEM | DESCRIPTION | QTY | UNIT |
| 464-0001 | 24” STORM HDPE N12 | 180 | LF |
| 644-6001 | IN SM SN SUP&AM TY10BWG (1) SA(P) | 11 | EA |
| 644-6060 | IN SM SN SUP&AM TYWT (1) WS (P) | 8 | EA |
| 677-6001 | ELIM EXIST PM 4” | 3400 | LF |
| 677-6003 | ELIN EXIST PM 8” | 97 | LF |
| 677-6005 | ELIM EXIST PM 12” | 231 | LF |
| 999-WC04 | LOWERED FIBER OPTIC CABLE | 1 | EA |
| 999-WC05 | 5% MARK-UP FOR SUB (STRIPING) | 1 | LS |
This Change Order results in a net increase of $26,798.12 to the Contract amount, for an adjusted Contract total of $5,002,313.21. The original Contract amount was $4,975,515.09. As a result of this and all Change Orders to-date, $26,798.12 has been added the Contract, resulting in an 0.54% net increase in the Contract cost. No additional days will be added to or deducted from the Contract because of this Change Order.
Fiscal Impact
| From/To | Acct No. | Description | Amount |
|---|
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| County Judge Exec Asst. | Becky Pruitt | 09/08/2022 11:26 AM |
- Form Started By:
- Julissa Romero
- Started On:
- 09/08/2022 08:04 AM
- Final Approval Date:
- 09/08/2022