Commissioners Court - Regular Session
- Meeting Date:
- 06/06/2023
- Title:
- 22IFB141 - CR 258 Extension Change Order #3 (Steel Encasement)
- Submitted By:
- Julissa Vasquez, Road Bond
- Department:
- Road Bond
- Agenda Category:
- Regular Agenda Items
Information
Agenda Item
Discuss, consider, and take appropriate action regarding Change Order No. 3 in the amount of $22,263.50 for Project 22IFB141 CR 258 Extension (Joe Bland Construction) P: 277 Funding Source: Road Bond.
Background
This Change Order provides payment to the Contractor for additional work requested by the adjacent Developer. It was agreed on by the Developer and Williamson County to split the cost of the sleeve installation. The sleeves will be placed across Questa Trail and across CR 258 for future use. Please see attached Change Order for details.
This Change Order results in a net increase of $22,263.50 to the Contract amount, for an adjusted Contract total of $6,281,583.55. The original Contract amount was $5,836,754.36. As a result of this and all Change Orders to-date, $444,829.19 has been added to the Contract, resulting in a 7.62% net increase in the Contract cost. As a result of this Change Order, zero (0) days will be added to the contract.
This Change Order results in a net increase of $22,263.50 to the Contract amount, for an adjusted Contract total of $6,281,583.55. The original Contract amount was $5,836,754.36. As a result of this and all Change Orders to-date, $444,829.19 has been added to the Contract, resulting in a 7.62% net increase in the Contract cost. As a result of this Change Order, zero (0) days will be added to the contract.
Fiscal Impact
| From/To | Acct No. | Description | Amount |
|---|
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| County Judge Exec Asst. | Becky Pruitt | 06/01/2023 09:57 AM |
- Form Started By:
- Julissa Romero
- Started On:
- 05/31/2023 08:45 AM
- Final Approval Date:
- 06/01/2023