76.
Commissioners Court - Regular Session
Meeting Date:
09/12/2023
Title:
22IFB141 - CR 258 Extension Change Order #5 (LHISD Right Turn Lane)
Submitted By:
Julissa Vasquez, Road Bond
Department:
Road Bond
Agenda Category:
Regular Agenda Items

Information

Agenda Item

Discuss, consider, and take appropriate action regarding Change Order No. 5 in the amount of $539,623.96 for Project 22IFB141 CR 258 Extension (Joe Bland Construction) P: 277 Funding Source: Road Bond.

Background

This Change Order provides payment to the contractor for additional work requested by Liberty Hill ISD (LHISD). The contractor will widen CR 258 along the eastbound roadway, add a right turn lane with a new entrance to the proposed High School, and will relocate a portion of the Georgetown water line that is located under the proposed High School entrance. LHISD will reimburse the County 100%. Multiple items will be added by this Change Order. Please see attached.
 
This Change Order results in a net increase of $539,623.96 to the Contract amount, for an adjusted Contract total of $6,667,915.51. The original Contract amount was $5,836,754.36. As a result of this and all Change Orders to-date, $831,161.15 has been added to the Contract, resulting in a 14.24% net increase in the overall Contract cost. As a result of this Change Order, thirty-one (31) days will be added to the contract.

 

Fiscal Impact

Attachments

Form Review

Inbox Reviewed By Date
County Judge Exec Asst. Becky Pruitt 09/07/2023 11:13 AM
Form Started By:
Julissa Romero
Started On:
09/05/2023 08:29 AM
Final Approval Date:
09/07/2023