48.
Commissioners Court - Regular Session
Meeting Date:
01/30/2024
Title:
22IFB139 FM 3349 at US 79 - Change Order #9 (Revised TCP)
Submitted By:
Julissa Vasquez, Road Bond
Department:
Road Bond
Agenda Category:
Regular Agenda Items

Information

Agenda Item

Discuss, consider, and take appropriate action regarding Change Order No. 9 in the amount of ($368,749.53) for Project 22IFB139 FM 3349 at US 79 (James Construction) P: 332 Funding Source: Road Bond.

Background

This Change Order revises the as-bid Traffic Control Plan (TCP) and construction phasing of the FM 3349 project. The modified TCP allows the Contractor to work on both the North Bound and South Bound Frontage Roads simultaneously, resulting in significant savings on temporary detour work. The changes to the TCP and construction phasing do not impact the project completion date and results in savings on several other contract items.

This Change Order results in a net decrease of $368,749.53 to the Contract amount, for an adjusted Contract total of $83,415,584.43. The original Contract amount was $81,941,038.13.  As a result of this and all Change Orders to-date, $1,474,546.30 has been added to the Contract, resulting in an 1.8% net increase in the Contract cost.  No additional days will be added to or deducted from the Contract as a result of this Change Order. 
 

Fiscal Impact

Attachments

Form Review

Inbox Reviewed By Date
County Judge Exec Asst. Becky Pruitt 01/25/2024 10:27 AM
Form Started By:
Julissa Romero
Started On:
01/24/2024 02:27 PM
Final Approval Date:
01/25/2024