Title:
23IFB13 Bud Stockton Extension - Change Order #4 (Fence Repair)
Submitted By:
Julissa Vasquez, Road Bond
Department:
Road Bond
Agenda Category:
Regular Agenda Items

Information

Agenda Item

Discuss, consider, and take appropriate action regarding Change Order No. 4 in the amount of $2,905.00 for Project 23IFB13 Bud Stockton Extension (Cash Construction) P: 307 Funding Source: Road Bond.

Background

This Change Order compensates the Contractor for additional fence work along the Hawthorne Parcel. After the new fence was installed, it was decided that the T-post spacing was not adequate for the livestock. A portion of the newly installed fence was re-stretched, and additional T-posts were added to prevent future issues. Please see attached Change Order for additional details.

This Change Order results in a net increase of $2,905.00 to the Contract amount, for an adjusted Contract total of $5,760,950.62. The original Contract amount was $5,917,275.00. As a result of this and all Change Orders to-date, the Contract has been decreased by $156,324.38, resulting in a 2.64% net decrease in the overall Contract cost. As a result of this Change Order, (0) days will be added to the contract.

 

Fiscal Impact

Attachments

Form Review

Inbox Reviewed By Date
County Judge Exec Asst. Becky Pruitt 07/11/2024 10:20 AM
Form Started By:
Julissa Romero
Started On:
07/10/2024 10:38 AM
Final Approval Date:
07/11/2024