72.
Commissioners Court - Regular Session
Meeting Date:
02/25/2025
Title:
23IFB8 Corridor H - Sam Bass Road Change Order #7 (CORR Valves)
Submitted By:
Julissa Vasquez, Road Bond
Department:
Road Bond
Agenda Category:
Regular Agenda Items

Information

Agenda Item

Discuss, consider, and take appropriate action regarding Change Order No. 7 in the amount of $288,195.31 for Project 23IFB8 Corridor H - Sam Bass Road (Cash Construction) P: 462 Funding Source: Road Bond.

Background

This Change Order adds several items for additional work requested by the City of Round Rock (CORR) to accommodate water line improvements along Sam Bass for a Wyoming Springs permanent connection solution. This Change Order also includes the necessary work and materials for a temporary bypass plan. Multiple items will be added by this Change Order. Please see the attached Change Order.
This Change Order results in a net increase of $288,195.31 to the Contract amount, for an adjusted Contract total of $34,423,902.82. The original Contract amount was $36,145,959.00. As a result of this and all Change Orders to-date, $1,722,056.18 has been deducted from the Contract, resulting in a 4.76% net decrease in the Contract cost. No additional days will be added to or deducted from the Contract as a result of this Change Order.

Fiscal Impact

Attachments

Form Review

Inbox Reviewed By Date
County Judge Exec Asst. Delia Colon 02/19/2025 02:01 PM
Form Started By:
Julissa Romero
Started On:
02/08/2025 06:08 PM
Final Approval Date:
02/19/2025