Skip to main content

AgendaQuick™

View Agenda Item

44.
Commissioners Court - Regular Session
Meeting Date:
03/25/2025
Title:
Berry Springs Park Improvements (P559) - CMAR-Chasco Change Order #4
Submitted For:
Dale Butler
Submitted By:
Christy Matoska, Facilities Management
Department:
Facilities Management
Agenda Category:
Consent

Information

Agenda Item

Receive and acknowledge approval of Change Order No. 4 from Chasco Constructors, Ltd., LLP for the Berry Springs Park Addition Project to extend time only due to lighting materials delay and PEC, the electrical provider, which was approved by Williamson County Facilities Senior Project Manager, Angel Gomez, pursuant to the Commissioners Court’s prior delegation of change order approval authority pursuant to Loc. Gov’t Code Sec. 262.031.

Background

This change is for a time-only extension for the Berry Springs Park Addition. Williamson County Facilities Senior Project Manager, Angel Gomez, was delegated change order approval authority for this project on March 21st, 2023 by the Commissioners Court pursuant to Williamson County Facilities pursuant to Loc. Gov’t Code Sec. 262.031. This item is to acknowledge such approval and record the same into the minutes of the Commissioners Court.

Fiscal Impact

Attachments

Form Review

Inbox Reviewed By Date
Hal Hawes Andrea Schiele 03/20/2025 10:36 AM
County Judge Exec Asst. Andrea Schiele 03/20/2025 03:09 PM
Form Started By:
Christy Matoska
Started On:
03/17/2025 02:41 PM
Final Approval Date:
03/20/2025