37.
Commissioners Court - Regular Session
- Meeting Date:
- 11/18/2025
- Title:
- Final Plat for the Atlas Ranch Phase 1 Section 1 subdivision – Pct 4
- Submitted For:
- Adam Boatright
- Submitted By:
- Misti Schulz, Infrastructure
- Department:
- Infrastructure
- Agenda Category:
- Consent
Information
Agenda Item
Discuss, consider, and take appropriate action on ratifying and approving the final plat for the Atlas Ranch Phase 1 Section 1 subdivision – Precinct 4.
Background
This is the first section of the Atlas Ranch Ph 1 Sec 1 subdivision. It consists of 225 residential lots, 3 open space lots, 1 pond lot, 1 wastewater treatment plan lot, 1 utility lot, and 10,105 linear feet of new public roads. Roadway and drainage construction is not yet complete, but a performance bond in the amount of $5,233,859.34 has been posted with the County to cover the cost of the remaining construction. Pursuant to the Commissioners Court action taken September 10, 2019, the County Engineer has approved this final plat in order to meet the review timelines set forth in House Bill 3167.
Timeline
2025-05-06 – initial submittal of the final plat
2025-06-05 – 1st review complete with comments
2025-06-27 – 2nd submittal of final plat
2025-07-11 – 2nd review complete with comments
2025-08-20 – 3rd submittal of final plat
2025-09-04 – 3rd review complete with comments
2025-09-15 – 4th submittal of final plat
2025-09-29 – 4th review complete with comments
2025-09-29 – 5th submittal of final plat
2025-10-13 – 5th review complete with comments
2025-10-14 – 6th submittal of final plat
2025-10-14 – 6th review complete with comments cleared
2025-10-27 – receipt of final plat with signatures
2025-11-10 – County Engineer approval letter sent
2025-11-10 – final plat placed on the November 18th, 2025 Commissioners Court agenda for consideration
Timeline
2025-05-06 – initial submittal of the final plat
2025-06-05 – 1st review complete with comments
2025-06-27 – 2nd submittal of final plat
2025-07-11 – 2nd review complete with comments
2025-08-20 – 3rd submittal of final plat
2025-09-04 – 3rd review complete with comments
2025-09-15 – 4th submittal of final plat
2025-09-29 – 4th review complete with comments
2025-09-29 – 5th submittal of final plat
2025-10-13 – 5th review complete with comments
2025-10-14 – 6th submittal of final plat
2025-10-14 – 6th review complete with comments cleared
2025-10-27 – receipt of final plat with signatures
2025-11-10 – County Engineer approval letter sent
2025-11-10 – final plat placed on the November 18th, 2025 Commissioners Court agenda for consideration
Fiscal Impact
| From/To | Acct No. | Description | Amount |
|---|
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| County Judge Exec Asst. | Andrea Schiele | 11/10/2025 06:46 PM |
- Form Started By:
- Misti Schulz
- Started On:
- 11/10/2025 12:59 PM
- Final Approval Date:
- 11/10/2025