Discuss, consider, and take appropriate action on ratification and approval of the revised preliminary plat for the Santa Rita Ranch Phase 7C subdivision (revision 1) – Precinct 2.
Public Background
This is the first revision to the preliminary plat of the Santa Rita Ranch Ph 7C subdivision that was last approved on May 23rd, 2023. Since the last approval, the developer has requested changes to the road alignments and lot layout. This revision consists of an increase of 3,121 linear feet of new public roads, an increase of 7 open space/PUE/landscape easement lots, 8 single family lots, and removal of the future LHISD school lot. With this revision, the proposed Santa Rita Ranch Ph 7C subdivision consists of 1 open space/drainage easement/PUE/landscape easement lot, 14 open space/PUE/landscape easements lots, 352 single family lots and 15,432 linear feet of new public roads on 103.056 acres. Pursuant to the Commissioners Court action taken September 10th, 2019, the County Engineer has approved this preliminary plat in order to meet the review timelines set forth in House Bill 3167.
Timeline
2025-12-23 – initial submittal of the preliminary plat
2026-01-22 – 1st review complete with comments
2026-02-28 – 2nd submittal of preliminary plat
2026-03-16 – 2nd review complete with comments
2026-03-20 – 3rd submittal of preliminary plat
2026-04-03 – 3rd review complete with comments
2026-05-15 – 4th submittal of preliminary plat
2026-05-25 – 4th review complete with comments cleared
2026-05-26– County Engineer approval letter sent
2026-05-26 – preliminary plat placed on the June 2nd, 2026 Commissioners Court agenda for consideration
Timeline
2025-12-23 – initial submittal of the preliminary plat
2026-01-22 – 1st review complete with comments
2026-02-28 – 2nd submittal of preliminary plat
2026-03-16 – 2nd review complete with comments
2026-03-20 – 3rd submittal of preliminary plat
2026-04-03 – 3rd review complete with comments
2026-05-15 – 4th submittal of preliminary plat
2026-05-25 – 4th review complete with comments cleared
2026-05-26– County Engineer approval letter sent
2026-05-26 – preliminary plat placed on the June 2nd, 2026 Commissioners Court agenda for consideration
Fiscal Impact
| From/To | Acct No. | Description | Amount |
|---|
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| County Judge Exec Asst. | Andrea Schiele | 05/26/2026 11:24 PM |
- Form Started By:
- Misti Schulz
- Started On:
- 05/26/2026 09:33 AM
- Final Approval Date:
- 05/26/2026