38.
Commissioners Court - Regular Session
- Meeting Date:
- 03/21/2017
- Title:
- 1603-062 CR 258 Change Order No. 04
- Submitted By:
- Dawn Haggard, Road Bond
- Department:
- Road Bond
- Agenda Category:
- Regular Agenda Items
Information
Agenda Item
Discuss, consider, and take any appropriate action regarding Change Order No. 4 in the amount of $14,907.69 for CR 258, a Road Bond Project in Commissioner Pct. 2.
Background
This change order compensates the Contractor for additional costs to locate and avoid impacts to the AT&T line and to maintain uninterrupted service to adjacent properties. Utilities AT&T and PEC were scheduled to be clear by August 31, 2016, but were not clear until February 2017. The Contractor worked to avoid impacts to the existing AT&T line during the installation of the new City of Georgetown waterline.
Fiscal Impact
| From/To | Acct No. | Description | Amount |
|---|
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| County Judge Exec Asst. | Wendy Coco | 03/15/2017 10:12 AM |
- Form Started By:
- dhaggard
- Started On:
- 03/14/2017 12:40 PM
- Final Approval Date:
- 03/15/2017