17.
Commissioners Court - Regular Session
- Meeting Date:
- 10/23/2018
- Title:
- North Campus Facility P324 - Change Order 65
- Submitted By:
- Gina Wrehsnig, Infrastructure
- Department:
- Infrastructure
- Division:
- Building Maintenance
- Agenda Category:
- Regular Agenda Items
Information
Agenda Item
Discuss, consider and take appropriate action on the Williamson County North Campus Project; Change Order # 65 from Vaughn Construction in the amount of $80,526.00 to approve funding from within the existing contract for general conditions and a fuel station tank liner. This change order is being funded by Buyout Savings.
Background
This change order is to approve the use of funds that are already inside of the GMP contract to fund additional general conditions due to the extended contract schedule to complete the fuel station and to add a tank liner to the DEF tank excavation for environmental protections.
Fiscal Impact
| From/To | Acct No. | Description | Amount |
|---|
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| County Judge Exec Asst. | Wendy Coco | 10/18/2018 11:40 AM |
- Form Started By:
- Gina Wrehsnig
- Started On:
- 10/18/2018 11:38 AM
- Final Approval Date:
- 10/18/2018