41.
Commissioners Court - Regular Session
- Meeting Date:
- 02/05/2019
- Title:
- Discuss consider and take appropriate action on approval of the final plat for the Rancho Sienna Section 13A & 13B subdivision - Pct 3
- Submitted For:
- Terron Evertson
- Submitted By:
- Adam Boatright, Infrastructure
- Department:
- Infrastructure
- Division:
- Road & Bridge
- Agenda Category:
- Regular Agenda Items
Information
Agenda Item
Discuss, consider and take appropriate action on approval of the final plat for the Rancho Sienna Section 13A & 13B subdivision - Precinct 3.
Background
This is the next section of the Rancho Sienna development. This phase consists of 103 single family lots, 6 open space lots, 1 open space/drainage lot and 3,743 feet of new public roads. Roadway and drainage construction are not yet complete, but a performance bond in the amount of $93,359.50 has been posted with the County to cover the cost of the remaining construction.
Timeline
2018-06-01 – 1st submittal of final plat
2018-08-31 – 1st review with comments
2018-11-28 – 2nd submittal of final plat
2019-01-10 – 2nd review complete, comments clear other than completing construction or bonding
2019-01-25 – 3rd submittal of final plat with all signatures
2019-01-30 – performance bond in the amount of $93,359.50 received for the remaining asphalt paving
2019-01-31 – final plat placed on 2019-02-05 Court agenda
Timeline
2018-06-01 – 1st submittal of final plat
2018-08-31 – 1st review with comments
2018-11-28 – 2nd submittal of final plat
2019-01-10 – 2nd review complete, comments clear other than completing construction or bonding
2019-01-25 – 3rd submittal of final plat with all signatures
2019-01-30 – performance bond in the amount of $93,359.50 received for the remaining asphalt paving
2019-01-31 – final plat placed on 2019-02-05 Court agenda
Fiscal Impact
| From/To | Acct No. | Description | Amount |
|---|
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| County Judge Exec Asst. | Andrea Schiele | 01/31/2019 02:10 PM |
- Form Started By:
- Adam Boatright
- Started On:
- 01/31/2019 10:55 AM
- Final Approval Date:
- 01/31/2019