- T1740 Sam Bass Interim Signals CO #04 (Final Balancing)
- Submitted By:
- Mayra Ramos, Road Bond
- Department:
- Road Bond
- Agenda Category:
- Regular Agenda Items
Information
Agenda Item
Discuss, consider, and take appropriate action regarding Change Order No. 4 in the amount of $3,055.00 for Project T1740 Sam Bass Interim Signals (Austin Traffic Signal), a Road Bond project in Commissioner Pct. 1 P:462 Funding Source: Road Bond.
Background
This Change Order provides the final quantities for the overrun/underrun of Contract items on the project. The project required the use of 7 (seven) timber poles for the signals instead of the 4 (four) that were previously reported.
This Change Order results in an increase of $3,055.00 to the Contract amount, for an adjusted Contract total of $307,008.36. The original Contract amount was $319,866.00. Because of this and all other Change Orders, $12,857.64 has been deducted from the Contract, resulting in a 4.0% net decrease in the Contract cost.
This Change Order results in an increase of $3,055.00 to the Contract amount, for an adjusted Contract total of $307,008.36. The original Contract amount was $319,866.00. Because of this and all other Change Orders, $12,857.64 has been deducted from the Contract, resulting in a 4.0% net decrease in the Contract cost.
Fiscal Impact
| From/To | Acct No. | Description | Amount |
|---|
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| County Judge Exec Asst. | Becky Pruitt | 12/02/2021 09:19 AM |
- Form Started By:
- mayra.ramos
- Started On:
- 12/01/2021 11:37 AM
- Final Approval Date:
- 12/02/2021