40.
Commissioners Court - Regular Session
- Meeting Date:
- 06/07/2022
- Title:
- T5045 - CR 404 Hutto Water Line Realignment - Change Order #1(Water Line Size)
- Submitted By:
- Julissa Vasquez, Road Bond
- Department:
- Road Bond
- Agenda Category:
- Regular Agenda Items
Information
Agenda Item
Discuss, consider, and take appropriate action regarding Change Order No. 6 in the amount of ($232,550.27) for Project T5045 - CR 404 Hutto Water Line Realignment (Austin Underground, Inc.) Funding Source: Road Bond P390.
Background
This Change Order revises the original water line pipe design from 18 inch ductile iron to 24 inch HDPE pipe. The change in pipe size and material was necessary to meet the increased demand in water and to alleviate the availability issues of ductile iron pipe. Due to the Contract value of this requested change, the 24 inch HDPE pipe material and the fusion of that pipe is also being removed from this Contract (T5045) and will be bid under a separate Contract (22IFB96). Portable concrete traffic barrier (CTB) is also being added to the Contract, to improve the work zone safety.
The following new items will be added by this Change Order.
This Change Order results in a net decrease of $232,550.27 to the Contract amount, for an adjusted Contract total of $2,665,088.73. The original Contract amount was $2,897,639.00. As a result of this and all Change Orders to-date, $232,550.27 has been deducted from the Contract, resulting in an 8.03% net decrease in the overall Contract cost. As a result of this Change Order, (0) days will be added to the contract.
The following new items will be added by this Change Order.
| ITEM | DESCRIPTION | QTY | UNIT |
| 512-6001 | PORT CTB (FURN & INSTL)(SGL SLOPE)(TY 1) | 120.00 | LF |
| 512-6049 | PORT CTB (REMOV)(SGL SLOPE)(TY 1) | 120.00 | LF |
| 545-6005 | CRASH CUSHION ATTEN. (REMOV) | 4.00 | EA |
| 545-6019 | CRASH CUSHION ATTEN. (INSTL)(S)(N)(TL3) | 4.00 | EA |
| 501S-36 | Jacking or Boring, 36" Steel Pipe, ASTM A134 | 789.00 | LF |
| G4.05 | Concrete Trench Cap (6" Thick, 2000 PSI) | 5.00 | CY |
| SP.W3.21.G | Valves, Butterfly 24" Dia. | 11.00 | EA |
| SP.W3.21.F | Drain Valve Assembly, including valve and pipe | 10.00 | EA |
| SS.W5.9.B24 | 24" HDPE Fittings | 10.00 | EA |
| SS.W5.9.C24 | 24" HDPE MJ Adapter | 24.00 | EA |
| SS.W5.9.C6 | 6" HDPE MJ Adapter | 10.00 | EA |
| SS.W5.9.A24-IO | Pipe, 24" Dia. HDPE (DIPS Size), DR11 (200psi), Complete in Place, excavation and backfill (Materials and Fusion not included) | 14,967.00 | LF |
This Change Order results in a net decrease of $232,550.27 to the Contract amount, for an adjusted Contract total of $2,665,088.73. The original Contract amount was $2,897,639.00. As a result of this and all Change Orders to-date, $232,550.27 has been deducted from the Contract, resulting in an 8.03% net decrease in the overall Contract cost. As a result of this Change Order, (0) days will be added to the contract.
Fiscal Impact
| From/To | Acct No. | Description | Amount |
|---|
Attachments
- T5045-CR 404 Hutto Water Line Realignment Change Order #1
- T5045-CR 404 Hutto Water Line Realignment Change Order #1
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| County Judge Exec Asst. | Becky Pruitt | 06/02/2022 10:01 AM |
- Form Started By:
- Julissa Romero
- Started On:
- 06/01/2022 07:30 AM
- Final Approval Date:
- 06/02/2022