Commissioners Court - Regular Session
- Meeting Date:
- 10/04/2022
- Title:
- 1812-282 Seward Junction Improvements CO#13 (Final Balancing)
- Submitted By:
- Julissa Vasquez, Road Bond
- Department:
- Road Bond
- Agenda Category:
- Regular Agenda Items
Information
Agenda Item
Discuss, consider, and take appropriate action regarding Change Order No. 13 in the amount of $371.75 for Project 1812-282 Seward Junction Improvements (Jordan Foster Construction) P: 271, P274 Funding Source: Road Bond.
Background
This Change Order provides the final balancing for the overrun/underrun of Contract quantities on the project as a result of addressing field conditions not accounted for in the original plans.
This Change Order results in a net increase of $371.75 to the Contract amount, for an adjusted Contract total of $12,839,851.12. The original Contract amount was $13,270,258.10. As a result of this and all Change Orders to-date, $430,406.98 has been deducted from the Contract, resulting in a 3.24% net decrease in the overall Contract cost. As a result of this Change Order, (0) days will be added to the contract.
This Change Order results in a net increase of $371.75 to the Contract amount, for an adjusted Contract total of $12,839,851.12. The original Contract amount was $13,270,258.10. As a result of this and all Change Orders to-date, $430,406.98 has been deducted from the Contract, resulting in a 3.24% net decrease in the overall Contract cost. As a result of this Change Order, (0) days will be added to the contract.
Fiscal Impact
| From/To | Acct No. | Description | Amount |
|---|
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| County Judge Exec Asst. | Becky Pruitt | 09/29/2022 10:43 AM |
- Form Started By:
- Julissa Romero
- Started On:
- 09/29/2022 07:00 AM
- Final Approval Date:
- 09/29/2022