43.
Commissioners Court - Regular Session
- Meeting Date:
- 08/22/2023
- Title:
- 23IFB8 Corridor H Sam Bass Rd. - Change Order #2 (Driveway Corrections)
- Submitted By:
- Julissa Vasquez, Road Bond
- Department:
- Road Bond
- Agenda Category:
- Regular Agenda Items
Information
Agenda Item
Discuss, consider, and take appropriate action regarding Change Order No. 2 in the amount of $5,250.00 for Project 23IFB8 Corridor H - Sam Bass Rd. (Cash Construction) P: 462 Funding Source: Road Bond.
Background
This Change Order updates incorrect unit prices that were inadvertently used for two existing items in Change Order 1. Please see the attached Change Order.
This Change Order results in a net increase of $5,250.00 to the Contract amount, for an adjusted Contract total of $33,757,130.88. The original Contract amount was $36,145,959.00. As a result of this and all Change Orders to-date, $2,388,828.12 has been deducted from the Contract, resulting in a 6.61% net decrease in the overall Contract cost. No time will be added to the Contract for this Change Order at this time.
This Change Order results in a net increase of $5,250.00 to the Contract amount, for an adjusted Contract total of $33,757,130.88. The original Contract amount was $36,145,959.00. As a result of this and all Change Orders to-date, $2,388,828.12 has been deducted from the Contract, resulting in a 6.61% net decrease in the overall Contract cost. No time will be added to the Contract for this Change Order at this time.
Fiscal Impact
| From/To | Acct No. | Description | Amount |
|---|
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| County Judge Exec Asst. | Becky Pruitt | 08/17/2023 07:38 AM |
- Form Started By:
- Julissa Romero
- Started On:
- 08/15/2023 01:08 PM
- Final Approval Date:
- 08/17/2023