22IFB39 - CR 111 Westinghouse Rd Change Order #11 (City of Georgetown WL)
Submitted By:
Julissa Vasquez, Road Bond
Department:
Road Bond
Agenda Category:
Regular Agenda Items

Information

Agenda Item

Discuss, consider, and take appropriate action regarding Change Order No. 11 in the amount of $81,433.12 for Project 22IFB39 CR 111 Westinghouse Rd (Capital Excavation) P: 292 Funding Source: Road Bond.

Background

This Change Order provides compensation to Contractor for relocating a City of Georgetown water line that is in conflict with the proposed driveway culvert. Please see attached Change Order for additional information. 

This Change Order results in an increase of $81,433.12 to the Contract amount, for an adjusted Contract total of $22,244,981.80. The original Contract amount was $21,024,332.88. As a result of this and previous Change Orders, $1,220,648.92 has been added to the Contract, resulting in a 5.81% increase in the Contract cost. As a result of this Change Order, zero (0) days will be added to the Contract.

Fiscal Impact

Attachments

Form Review

Inbox Reviewed By Date
County Judge Exec Asst. Becky Pruitt 08/17/2023 07:38 AM
Form Started By:
Julissa Romero
Started On:
08/16/2023 12:38 PM
Final Approval Date:
08/17/2023