32.
Commissioners Court - Regular Session
- Meeting Date:
- 11/21/2023
- Title:
- Sheriff's Administration Office Facade Repairs - Change Order #1
- Submitted For:
- Dale Butler
- Submitted By:
- Christy Matoska, Facilities Management
- Department:
- Facilities Management
- Agenda Category:
- Consent
Information
Agenda Item
Discuss, consider and take appropriate action on a change order from Falkenberg Construction Co., Inc. for an increase in substantial completion, for an additional 72 business days. New substantial completion date is January 19th, 2024.
Background
This change order is for Falkenberg Construction Co., Inc. to increase the substantial completion date by 72 days. The new substantial completion date will be 1/19/2024.
Fiscal Impact
| From/To | Acct No. | Description | Amount |
|---|
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| County Judge Exec Asst. | Becky Pruitt | 11/15/2023 09:24 AM |
- Form Started By:
- Christy Matoska
- Started On:
- 11/15/2023 09:15 AM
- Final Approval Date:
- 11/15/2023