37.
Commissioners Court - Regular Session
Meeting Date:
04/29/2025
Title:
RM 620/SH 45 Intersection to McNeil Rd - HDR - SWA#4 to WA#2
Submitted By:
Marie Walters, Road Bond
Department:
Road Bond
Agenda Category:
Consent

Information

Agenda Item

Discuss, consider, and take appropriate action on Supplement No. 4 to Work Authorization No. 2 to the RM 620/SH 45 Intersection to McNeil Road contract executed on March 18, 2021, between Williamson County and HDR Engineering, Inc. relating to the 2019 Road Bond Program. Project: P338 Fund Source: Road Bonds

Background

The HDR Engineering, Inc. Supplemental No. 4 to Work Authorization No. 2 extends the termination date to 5/31/2025. This WA amount stays under the contract cap.
 

Fiscal Impact

Attachments

Form Review

Inbox Reviewed By Date
County Judge Exec Asst. Andrea Schiele 04/24/2025 02:53 PM
Form Started By:
Marie Walters
Started On:
04/18/2025 08:56 AM
Final Approval Date:
04/24/2025