66.
Commissioners Court - Regular Session
Meeting Date:
09/09/2025
Title:
25IFB9 CR 255 Realignment - Change Order #2 (Revised TCP)
Submitted By:
Julissa Romero, Road Bond
Department:
Road Bond
Agenda Category:
Regular Agenda Items

Information

Agenda Item

Discuss, consider, and take appropriate action regarding Change Order No. 2 in the amount of $40,644.93 for Project 25IFB9 CR 255 Realignment (Jordan Foster Construction).

Background

This Change Order compensates the Contractor for implementing additional safety measures along Ronald Reagan Blvd at CR 255. Due to the high traffic volume and speed at this location, concrete traffic barriers will be installed to protect workers within the work zone. The speed limit will also be reduced to 50 mph during the widening process. Message boards will be placed 8 days prior to the start of construction, to notify the traveling public per Williamson County's request. The Contractor provided signed and sealed Traffic Control Plan (TCP) sheets for this change. Please see the attached Change Order for additional details. 

This Change Order results in a net increase of $40,644.93 to the Contract amount, for an adjusted Contract total of $20,874,710.34. The original Contract amount was $20,847,300.93. As a result of this and all Change Orders to-date, $27,409.41 has been added to the Contract, resulting in a 0.13% net increase in the Contract cost. No additional days will be added to or deducted from the Contract as a result of this Change Order.

P: 546 Funding Source: Road and Bridge in Commissioner Precinct 3.

Fiscal Impact

Attachments

Form Review

Inbox Reviewed By Date
County Judge Exec Asst. Andrea Schiele 08/29/2025 03:06 PM
Form Started By:
Julissa Romero
Started On:
08/26/2025 06:15 PM
Final Approval Date:
08/29/2025