64.
Commissioners Court - Regular Session
- Meeting Date:
- 09/09/2025
- Title:
- 24IFB38 Ronald Reagan Blvd Milling and Overlay - Change Order #1 - Balancing
- Submitted For:
- Matt Williamson
- Submitted By:
- Jenifer Favreau, Infrastructure
- Department:
- Infrastructure
- Division:
- Road & Bridge
- Agenda Category:
- Regular Agenda Items
Information
Agenda Item
Discuss, consider and take appropriate action on Change Order No 1 to contract number 24IFB38 for Texas Materials Group, Inc. a reduction in the amount of $124,893.95 for Ronald W. Reagan Blvd Milling and Overlay. Funding Source: 01.0200.0210.003599.
Background
This change order is a balancing change order. All work has been completed. The original contract amount was $3,389,603.55. With the reduction of this Change Order in the amount of $124,893.95, the final contract amount will be $3,264,709.60. This change order decreases the original contract by 3.68%.
Fiscal Impact
| From/To | Acct No. | Description | Amount |
|---|
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| County Judge Exec Asst. | Delia Colon | 09/02/2025 08:32 AM |
- Form Started By:
- Jenifer Favreau
- Started On:
- 09/02/2025 08:10 AM
- Final Approval Date:
- 09/02/2025