- 24IFB57 Ronald Reagan Blvd. Widening - Change Order #6 (Misc Items)
- Submitted By:
- Julissa Romero, Road Bond
- Department:
- Road Bond
- Agenda Category:
- Regular Agenda Items
Information
Agenda Item
Discuss, consider, and take appropriate action regarding Change Order No. 6 in the amount of $12,886.00 for Project 24IFB57 Ronald Reagan Blvd. Widening (Chasco Constructors).
Background
This Change Order adds drainage items and adjusts quantities for the installation of a temporary culvert underneath the roadway just south of Kauffman Loop per RFI 42. This Change Order also compensates the Contractor for replacing an inlet with a safety end treatment and grading per RFI 74. This Change Order also adds items to the Contract for the installation of a concrete cap, and temporary construction crossing over the Enterprise gas lines per Enterprise requirements and stated in the Letter of No Objection (LONO). Lastly, this Change Order includes a monthly rate for an additional message board required at Kauffman Loop, which will also be available for additional use as needed. Multiple items will be added by this Change Order. Please see attached Change Order.
This Change Order results in a net increase of $12,886.00 to the Contract amount, for an adjusted Contract total of $52,482,748.50. The original Contract amount was $52,159,299.00. As a result of this and all Change Orders to-date, $323,449.50 has been added to the Contract, resulting in a 0.62% net increase in the Contract cost. No additional days will be added to or deducted from the Contract as a result of this Change Order.
Project: P336 Funding Source: 2019 Road Bond in Commissioners Precinct 2.
This Change Order results in a net increase of $12,886.00 to the Contract amount, for an adjusted Contract total of $52,482,748.50. The original Contract amount was $52,159,299.00. As a result of this and all Change Orders to-date, $323,449.50 has been added to the Contract, resulting in a 0.62% net increase in the Contract cost. No additional days will be added to or deducted from the Contract as a result of this Change Order.
Project: P336 Funding Source: 2019 Road Bond in Commissioners Precinct 2.
Fiscal Impact
| From/To | Acct No. | Description | Amount |
|---|
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| County Judge Exec Asst. | Andrea Schiele | 09/24/2025 07:46 AM |
- Form Started By:
- Julissa Romero
- Started On:
- 09/21/2025 01:00 PM
- Final Approval Date:
- 09/24/2025