64.
Commissioners Court - Regular Session
Meeting Date:
11/04/2025
Title:
23IFB67 Corridor C - SH29 Bypass Change Order #3 (Balancing)
Submitted By:
Julissa Romero, Road Bond
Department:
Road Bond
Agenda Category:
Regular Agenda Items

Information

Agenda Item

Discuss, consider, and take appropriate action regarding Change Order No. 3 in the amount of ($373,288.56) for Project 23IFB67 Corridor C - SH29 Bypass (Capital Excavation).

Background

This Change Order adjusts the excavation and embankment items due to the landscape of the project changing from the time of the design to construction. This Change Order also provides the final balancing for the overruns/underruns of contract quantities on the project that are a result of addressing field conditions not accounted for in the original plans. Multiple items will be added by this Change Order. Please see attached Change Order for additional details.

This Change Order results in a net decrease of $373,288.56 to the Contract amount, for an adjusted Contract total of $30,183,328.97. The original Contract amount was $30,540,848.03. As a result of this and all Change Orders to-date, $357,519.06 has been deducted from the Contract, resulting in an 1.17% net decrease in the Contract cost. Zero (0) days will be deducted from the Contract as a result of this Change Order.

P: 459 Funding Source Bond in Commissioners Precinct 4.

Fiscal Impact

Attachments

Form Review

Inbox Reviewed By Date
County Judge Exec Asst. Delia Colon 10/29/2025 08:22 AM
Form Started By:
Julissa Romero
Started On:
10/28/2025 08:54 AM
Final Approval Date:
10/29/2025