- CR 305 – RS&H – SWA#3 to WA#1
- Submitted By:
- Ragan Riggs, Road Bond
- Department:
- Road Bond
- Agenda Category:
- Consent
Information
Agenda Item
Discuss, consider, and take appropriate action on Supplemental No. 3 to Work Authorization No. 1 to the CR 305 contract executed on March 19, 2024, between Williamson County and RS&H, Inc. relating to the 2023 Road Bond Program.
Background
RS&H, Inc. Supplemental No. 3 to Work Authorization No. 1 extends the termination date to January 31, 2026. Project: P686 Fund Source: Road Bond