31.
Commissioners Court - Regular Session
- Meeting Date:
- 12/09/2025
- Title:
- Corridor A3 – LJA – SWA#2 to WA#1
- Submitted By:
- Ragan Riggs, Road Bond
- Department:
- Road Bond
- Agenda Category:
- Consent
Information
Agenda Item
Discuss, consider, and take appropriate action on Supplemental No. 2 to Work Authorization No. 1 to the Corridor A3 contract executed on December 18, 2024, between Williamson County and LJA Engineering, Inc. relating to the LTP/Corridor Program.
Background
This Supplemental No. 2 to Work Authorization No. 1 extends the termination date to February 28, 2026. Project: P630 Fund Source: LTP/Corridor Program.
Fiscal Impact
| From/To | Acct No. | Description | Amount |
|---|
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| County Judge Exec Asst. | Andrea Schiele | 12/03/2025 09:23 AM |
- Form Started By:
- Ragan Riggs
- Started On:
- 12/01/2025 10:22 AM
- Final Approval Date:
- 12/03/2025