28.
Commissioners Court - Regular Session
- Meeting Date:
- 07/21/2026
- Title:
- Preliminary plat for the JMA Len Bar Commercial subdivision – Pct 2
- Submitted For:
- Adam Boatright
- Submitted By:
- Misti Schulz, Infrastructure
- Department:
- Infrastructure
- Agenda Category:
- Consent
Information
Agenda Item
Discuss, consider, and take appropriate action on ratification and approval of the preliminary plat for the JMA Len Bar Commercial subdivision – Precinct 2.
Public Background
This proposed subdivision consists of 1 commercial lot and no new roads on 5.74 acres. Pursuant to the Commissioners Court action taken September 10th, 2019, the County Engineer has approved this preliminary plat in order to meet the review timelines set forth in House Bill 3167.
Timeline
2026-05-01 – initial submittal of the preliminary plat
2026-05-29 – 1st review complete with comments
2026-06-05 – 2nd submittal of preliminary plat
2026-06-18 – 2nd review complete with comments
2026-07-01 – 3rd submittal of preliminary plat
2026-07-13 – 3rd review complete with comments cleared
2026-07-13 – County Engineer approval letter sent
2026-07-14 – preliminary plat placed on the July 21st, 2026 Commissioners Court agenda for consideration
Timeline
2026-05-01 – initial submittal of the preliminary plat
2026-05-29 – 1st review complete with comments
2026-06-05 – 2nd submittal of preliminary plat
2026-06-18 – 2nd review complete with comments
2026-07-01 – 3rd submittal of preliminary plat
2026-07-13 – 3rd review complete with comments cleared
2026-07-13 – County Engineer approval letter sent
2026-07-14 – preliminary plat placed on the July 21st, 2026 Commissioners Court agenda for consideration
Fiscal Impact
| From/To | Acct No. | Description | Amount |
|---|
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| County Judge Exec Asst. | Delia Colon | 07/15/2026 08:35 AM |
- Form Started By:
- Misti Schulz
- Started On:
- 07/14/2026 04:11 PM
- Final Approval Date:
- 07/15/2026