Commissioners Court - Regular Session
- Meeting Date:
- 05/16/2017
- Title:
- 1604-068 Forest North Ph 1 Change Order No. 2
- Submitted By:
- Dawn Haggard, Road Bond
- Department:
- Road Bond
- Agenda Category:
- Regular Agenda Items
Information
Agenda Item
Discuss, consider, and take appropriate action regarding Change Order No. 2 in the amount of $58,006.83 for Forest North Drainage Phase 1, a Road Bond Project in Commissioner Pct. 1.
Background
This Change Order compensates the Contractor for the removal and relocation of an existing waterline in conflict with a proposed storm sewer line. The conflict is located near the corner of Broadmeade Avenue and Braeburn Glen. The existing waterline was not shown on the City of Austin waterline plans and therefore was not known to be in conflict prior to the storm sewer installation. The Contractor has agreed to extend existing bid items to pay for this relocation work and has requested additional pay items with daily rates for de-watering the trench and the required traffic control. This Change Order also adds a pay item for trench repair for removal of existing asbestos water line required to be relocated.
Fiscal Impact
| From/To | Acct No. | Description | Amount |
|---|
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| County Judge Exec Asst. | Wendy Coco | 05/11/2017 08:33 AM |
- Form Started By:
- dhaggard
- Started On:
- 05/09/2017 05:17 PM
- Final Approval Date:
- 05/11/2017