23.
Commissioners Court - Regular Session
- Meeting Date:
- 09/12/2017
- Title:
- North Campus Facility - Change Order 18
- Submitted By:
- Gina Wrehsnig, Facilities Maintenance
- Department:
- Facilities Management
- Agenda Category:
- Consent
Information
Agenda Item
Discuss, consider and take appropriate action on accepting and approving a report on the North Campus Project; Change Order #18 in the amount of $1,747.00 to be paid from the Construction Manager’s Contingency for X-Bracing Modification.
Background
This change is modifications to X-bracing due to door frame locations. To be funded from the construction manager’s contingency with no change to the contract amount.
Fiscal Impact
| From/To | Acct No. | Description | Amount |
|---|
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| County Judge Exec Asst. | Wendy Coco | 09/07/2017 11:33 AM |
- Form Started By:
- Gina Wrehsnig
- Started On:
- 09/07/2017 11:20 AM
- Final Approval Date:
- 09/07/2017