North Campus Facility P324 - Change Order 48
Submitted By:
Gina Wrehsnig, Infrastructure
Department:
Infrastructure
Division:
Building Maintenance
Agenda Category:
Regular Agenda Items

Information

Agenda Item

Discuss, consider and take appropriate action on the Williamson County North Campus Project; Change Order #48 from Vaughn Construction in the amount of $35,771.00 to fund concrete work at infill gap along sidewalk and drive that was not included in the original scope of the project. This change order is being funded by the Owners Contingency.

Background

The scope of concrete work for this change order is necessary to prevent water intrusion underneath the asphalt paving of the driveway. This infill was not specified in the original design documents but was clarified in ASI-042.

Fiscal Impact

Attachments

Form Review

Inbox Reviewed By Date
County Judge Exec Asst. Wendy Coco 03/15/2018 11:21 AM
Form Started By:
Gina Wrehsnig
Started On:
03/15/2018 10:30 AM
Final Approval Date:
03/15/2018