Commissioners Court - Regular Session
- Meeting Date:
- 10/19/2021
- Title:
- Texas Materials Group T4230 Change Order No 1
- Submitted For:
- Terron Evertson
- Submitted By:
- Vicky Edwards, Infrastructure
- Department:
- Infrastructure
- Agenda Category:
- Regular Agenda Items
Information
Agenda Item
Discuss, consider and take appropriate action on Change Order No 1, to contract number IFB T4230, in the amount of $20,509.80 for CR 258 Milling, Sealing and Overlay. Funding Source: 01.0200.0210.003599.
Background
Original contract amount was $558,237.18. With the addition of this change order, of $20,509.80, new contract amount will be $578,746.98. The positive change order is the result of the need to place the topsoil along both sides of the roadway.
Fiscal Impact
| From/To | Acct No. | Description | Amount |
|---|
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| County Judge Exec Asst. | Becky Pruitt | 10/06/2021 09:51 AM |
- Form Started By:
- Vicky Edwards
- Started On:
- 10/05/2021 01:43 PM
- Final Approval Date:
- 10/06/2021