56.
Commissioners Court - Regular Session
- Meeting Date:
- 07/12/2022
- Title:
- T5045 - CR 404 Hutto Water Line Realignment Change Order #2 (Jonah Water Line)
- Submitted By:
- Julissa Vasquez, Road Bond
- Department:
- Road Bond
- Agenda Category:
- Regular Agenda Items
Information
Agenda Item
Discuss, consider, and take appropriate action regarding Change Order No. 2 in the amount of $625,239.52 for Project T5045 CR 404 Hutto Water Line Realignment (Austin Underground) P: 390b Funding Source: Road Bond.
Background
This Change Order adds the relocation of the Jonah Water line along CR 401 that is currently in conflict with the CR 401 Reconstruction project.
The following new items will be added by this Change Order.
This Change Order results in an increase of $625,239.52 to the Contract amount, for an adjusted Contract total of $3,290,328.25. The original Contract amount was $2,897,639.00. As a result of this and all Change Orders to-date, $392,689.25 has been added to the Contract, resulting in a 13.55% net increase to the overall Contract cost. Due to the current uncertainty in material lead times, time adjustments for this work will be deferred to a later time. Additional time will be determined once materials are on site and will only be granted after the completion of the original scope of work.
The following new items will be added by this Change Order.
| ITEM | DESCRIPTION | QUANTITY | UNIT |
| J106-01 | 4" C-900 DR-18 PVC Pipe and Fittings, w/ Tracer Wire; Installed | 1,372.00 | LF |
| J106-02 | 4" C-900 DR-18 PVC Restrained Joint Pipe and Fittings, w/ Tracer Wire; Installed | 202.00 | LF |
| J106-03 | 2" HDPE SDR 9 and Fittings; w/ Tracer Wire; Installed | 7.00 | LF |
| J106-04 | 20" Steel Enc. Pipe, Bored; w/ 4" Restrained Joint C900 DR18 PVC Pipe; Installed | 295.00 | LF |
| J106-05 | 20" Steel Enc. Pipe, Open Cut; w/ 4" Restrained Joint C900 DR18 PVC Pipe; Installed | 265.00 | LF |
| J106-06 | 8" Steel Enc. Pipe, Open Cut; w/ 4" Restrained Joint C900 DR18 PVC Pipe; Installed | 208.00 | LF |
| J106-07 | Concrete Encased; 8" Steel Enc. Pipe, Open Cut; 4" Restrained Joint C900 DR 18 PVC Pipe; Installed | 200.00 | LF |
| J106-08 | 4" Gate Valve, Box, and Marker; Installed | 9.00 | EA |
| J106-09 | Air/Vacuum Relief Valve Assembly and Marker; Installed | 1.00 | EA |
| J106-10 | Blow Off Valve Assembly And Marker; Installed | 2.00 | EA |
| J106-11 | Connect New 4" to Existing 4"; Installed | 2.00 | EA |
| J106-12 | Connect New 4" to Existing 2"; Installed | 3.00 | EA |
| J106-13 | Connect New 2" To Existing 1.5"; Installed | 1.00 | EA |
| J106-14 | Cap Existing 2" Line; Complete | 1.00 | EA |
| J106-15 | Trench Safety System Design and Implementation | 2,254.00 | LF |
| J106-16 | Traffic Control Plan Development And Implementation | 1.00 | LS |
| J106-17 | SWPPP Design and Implementation | 1.00 | LS |
| J106-18 | Mobilization (Not to Exceed 10% of Total Project Bid) | 1.00 | LS |
This Change Order results in an increase of $625,239.52 to the Contract amount, for an adjusted Contract total of $3,290,328.25. The original Contract amount was $2,897,639.00. As a result of this and all Change Orders to-date, $392,689.25 has been added to the Contract, resulting in a 13.55% net increase to the overall Contract cost. Due to the current uncertainty in material lead times, time adjustments for this work will be deferred to a later time. Additional time will be determined once materials are on site and will only be granted after the completion of the original scope of work.
Fiscal Impact
| From/To | Acct No. | Description | Amount |
|---|
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| County Judge Exec Asst. | Becky Pruitt | 07/07/2022 09:55 AM |
- Form Started By:
- Julissa Romero
- Started On:
- 07/06/2022 10:06 AM
- Final Approval Date:
- 07/07/2022