- 22IFB68 Wyoming Springs Intersection Improvements at Smyers Lane - Change Order #2 (Balancing)
- Submitted By:
- Julissa Vasquez, Road Bond
- Department:
- Road Bond
- Agenda Category:
- Regular Agenda Items
Information
Agenda Item
Discuss, consider, and take appropriate action regarding Change Order No. 2 in the amount of ($41,610.00) for Project 22IFB68 Wyoming Springs Intersection Improvements at Smyers Lane (MA Smith Contracting) P: 339 Funding Source: Road Bond.
Background
This Change Order provides the final balancing for the overrun/underrun of contract quantities on the project, as a result of addressing field conditions not accounted for in the original plans.
This Change Order results in a net decrease of $41,610.00 to the Contract amount, for an adjusted Contract total of $314,282.50. The original Contract amount was $355,892.50. As a result of this and all Change Orders to-date, $41,610.00 has been removed from the Contract, resulting in a 11.69% net decrease in the overall Contract cost. No time will be added to the Contract for this Change Order.
This Change Order results in a net decrease of $41,610.00 to the Contract amount, for an adjusted Contract total of $314,282.50. The original Contract amount was $355,892.50. As a result of this and all Change Orders to-date, $41,610.00 has been removed from the Contract, resulting in a 11.69% net decrease in the overall Contract cost. No time will be added to the Contract for this Change Order.
Fiscal Impact
| From/To | Acct No. | Description | Amount |
|---|
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| County Judge Exec Asst. | Becky Pruitt | 09/01/2022 09:10 AM |